Research article

Stochastic production-readiness design and order-acceptance scheduling in high-mix low-volume manufacturing

  • Published: 25 November 2026
  • 90B35, 90C11, 90C15, 90C27

  • High-mix low-volume manufacturing requires production readiness under uncertain orders and limited capacity. We formulate a two-stage stochastic model that selects product–machine readiness before demand and then jointly accepts and schedules orders with alternative machines, sequence-dependent setups, and deadlines. We establish complexity and structural results and develop exact component-wise logic-based Benders decomposition and a capability-aware matheuristic. In the focal study, 20 sample average approximation replications select the same network; the stochastic design achieves out-of-sample net value 145.89 versus 65.29 for a deterministic-medoid benchmark. Component-wise decomposition reduces master iterations from 47 to 20. Across 48 additional instances, the schedule-aware heuristic improves mean net value by 28.99 over an aggregate proxy (95% paired interval [14.89, 43.09]). However, a small-instance exact-recourse check finds a ranking reversal, so heuristic gains do not establish exact-policy superiority.

    Citation: Youngchul Kim, Chaehwa Lee, Hyeyoung Hwang, Jinho Cha, Hongsuk Park. Stochastic production-readiness design and order-acceptance scheduling in high-mix low-volume manufacturing[J]. Journal of Industrial and Management Optimization, 2026, 22(12): 6867-6907. doi: 10.3934/jimo.2026229

    Related Papers:

  • High-mix low-volume manufacturing requires production readiness under uncertain orders and limited capacity. We formulate a two-stage stochastic model that selects product–machine readiness before demand and then jointly accepts and schedules orders with alternative machines, sequence-dependent setups, and deadlines. We establish complexity and structural results and develop exact component-wise logic-based Benders decomposition and a capability-aware matheuristic. In the focal study, 20 sample average approximation replications select the same network; the stochastic design achieves out-of-sample net value 145.89 versus 65.29 for a deterministic-medoid benchmark. Component-wise decomposition reduces master iterations from 47 to 20. Across 48 additional instances, the schedule-aware heuristic improves mean net value by 28.99 over an aggregate proxy (95% paired interval [14.89, 43.09]). However, a small-instance exact-recourse check finds a ranking reversal, so heuristic gains do not establish exact-policy superiority.



    加载中


    [1]

    S. Dauzère-Pérès, J. Ding, L. Shen, K. Tamssaouet, The Flexible Job Shop Scheduling Problem: A Review, Eur. J. Oper. Res., 314 (2024), 409–432. https://doi.org/10.1016/j.ejor.2023.05.017

    doi: 10.1016/j.ejor.2023.05.017
    [2]

    C. Özgüven, L. Özbakır, Y. Yavuz, Mathematical Models for Job-Shop Scheduling Problems with Routing and Process Plan Flexibility, Appl. Math. Model., 34 (2010), 1539–1548. https://doi.org/10.1016/j.apm.2009.09.002

    doi: 10.1016/j.apm.2009.09.002
    [3]

    S. A. Slotnick, Order Acceptance and Scheduling: A Taxonomy and Review, Eur. J. Oper. Res., 212 (2011), 1–11. https://doi.org/10.1016/j.ejor.2010.09.042

    doi: 10.1016/j.ejor.2010.09.042
    [4]

    L. Xu, Q. Wang, S. Huang, Dynamic Order Acceptance and Scheduling Problem with Sequence-Dependent Setup Time, Int. J. Prod. Res., 53 (2015), 5797–5808. https://doi.org/10.1080/00207543.2015.1005768

    doi: 10.1080/00207543.2015.1005768
    [5]

    Q. Li, D. Zhang, S. Wang, I. Kucukkoc, A Dynamic Order Acceptance and Scheduling Approach for Additive Manufacturing On-Demand Production, Int. J. Adv. Manuf. Technol., 105 (2019), 3711–3729. https://doi.org/10.1007/s00170-019-03796-x

    doi: 10.1007/s00170-019-03796-x
    [6]

    M. Fu, R. G. Askin, J. W. Fowler, M. Zhang, Stochastic Optimization of Product–Machine Qualification in a Semiconductor Back-End Facility, IIE Trans., 47 (2015), 739–750. https://doi.org/10.1080/0740817X.2014.964887

    doi: 10.1080/0740817X.2014.964887
    [7]

    X. Chang, M. Dong, Stochastic Programming for Qualification Management of Parallel Machines in Semiconductor Manufacturing, Comput. Oper. Res., 79 (2017), 49–59. https://doi.org/10.1016/j.cor.2016.09.006

    doi: 10.1016/j.cor.2016.09.006
    [8]

    H. Li, W. T. Huh, M. C. Sampaio, N. Keng, Planning Production and Equipment Qualification under High Process Flexibility, Prod. Oper. Manag., 30 (2021), 3369–3390. https://doi.org/10.1111/poms.13439

    doi: 10.1111/poms.13439
    [9]

    T. Aouam, K. Geryl, K. Kumar, N. Brahimi, Production Planning with Order Acceptance and Demand Uncertainty, Comput. Oper. Res., 91 (2018), 145–159. https://doi.org/10.1016/j.cor.2017.11.013

    doi: 10.1016/j.cor.2017.11.013
    [10]

    F. Xiong, L. Jing, C. Xiang, Y. Han, Order Acceptance and Scheduling under Eligibility, Availability, and Budget Constraints in Distributed Heterogeneous Flow Shop Production, Expert Syst. Appl., 280 (2025), 127586. https://doi.org/10.1016/j.eswa.2025.127586

    doi: 10.1016/j.eswa.2025.127586
    [11]

    F. Tanrisever, D. J. Morrice, D. P. Morton, Managing Capacity Flexibility in Make-to-Order Production Environments, Eur. J. Oper. Res., 216 (2012), 334–345. https://doi.org/10.1016/j.ejor.2011.07.043

    doi: 10.1016/j.ejor.2011.07.043
    [12]

    W. C. Jordan, S. C. Graves, Principles on the Benefits of Manufacturing Process Flexibility, Manag. Sci., 41 (1995), 577–594. https://doi.org/10.1287/mnsc.41.4.577

    doi: 10.1287/mnsc.41.4.577
    [13]

    D. Simchi-Levi, Y. Wei, Understanding the Performance of the Long Chain and Sparse Designs in Process Flexibility, Oper. Res., 60 (2012), 1125–1141. https://doi.org/10.1287/opre.1120.1081

    doi: 10.1287/opre.1120.1081
    [14]

    G. Zhang, J. Sun, X. Liu, G. Wang, Y. Yang, Solving Flexible Job Shop Scheduling Problems with Transportation Time Based on Improved Genetic Algorithm, Math. Biosci. Eng., 16 (2019), 1334–1347. https://doi.org/10.3934/mbe.2019065

    doi: 10.3934/mbe.2019065
    [15]

    S. Yan, G. Zhang, J. Sun, W. Zhang, An Improved Ant Colony Optimization for Solving the Flexible Job Shop Scheduling Problem with Multiple Time Constraints, Math. Biosci. Eng., 20 (2023), 7519–7547. https://doi.org/10.3934/mbe.2023325

    doi: 10.3934/mbe.2023325
    [16]

    Y. Chen, H. Wang, C. Tsai, C. Wu, A Genetic Algorithm for Tool-Constrained Scheduling with Dynamic Expedited Orders in Smart Manufacturing, J. Ind. Manag. Optim., 22 (2026), 182–213. https://doi.org/10.3934/jimo.2026007

    doi: 10.3934/jimo.2026007
    [17]

    J. C. Chen, C. Wu, C. Chen, K. Chen, Flexible Job Shop Scheduling with Parallel Machines Using Genetic Algorithm and Grouping Genetic Algorithm, Expert Syst. Appl., 39 (2012), 10016–10021. https://doi.org/10.1016/j.eswa.2012.01.211

    doi: 10.1016/j.eswa.2012.01.211
    [18]

    M. Rowshannahad, S. Dauzère-Pérès, B. Cassini, Capacitated Qualification Management in Semiconductor Manufacturing, Omega, 54 (2015), 50–59. https://doi.org/10.1016/j.omega.2015.01.012

    doi: 10.1016/j.omega.2015.01.012
    [19]

    A. Perraudat, S. Dauzère-Pérès, P. Vialletelle, Robust Tactical Qualification Decisions in Flexible Manufacturing Systems, Omega, 106 (2022), 102537. https://doi.org/10.1016/j.omega.2021.102537

    doi: 10.1016/j.omega.2021.102537
    [20]

    A. Perraudat, S. Dauzère-Pérès, P. Vialletelle, Optimizing Multiple Qualifications of Products on Non-Identical Parallel Machines, Comput. Oper. Res., 144 (2022), 105813. https://doi.org/10.1016/j.cor.2022.105813

    doi: 10.1016/j.cor.2022.105813
    [21]

    J. Feng, H. Li, W. T. Huh, M. C. Sampaio, N. Keng, Erratum for "Planning Production and Equipment Qualification under High Process Flexibility", Prod. Oper. Manag., 31 (2022), 1890–1892. https://doi.org/10.1111/poms.13682

    doi: 10.1111/poms.13682
    [22]

    K. Tamssaouet, S. Dauzère-Pérès, On the Impact of Operation Flexibility in the Flexible Job-Shop Scheduling Problem, Omega, 144 (2026), 103591. https://doi.org/10.1016/j.omega.2026.103591

    doi: 10.1016/j.omega.2026.103591
    [23]

    M. Nattaf, S. Dauzère-Pérès, C. Yugma, C. Wu, Parallel Machine Scheduling with Time Constraints on Machine Qualifications, Comput. Oper. Res., 107 (2019), 61–76. https://doi.org/10.1016/j.cor.2019.03.004

    doi: 10.1016/j.cor.2019.03.004
    [24]

    X. Chang, M. Dong, Product–Machine Qualification Using a Process Flexibility Strategy Considering Capacity Loss, IISE Trans., 56 (2024), 98–113. https://doi.org/10.1080/24725854.2023.2202226

    doi: 10.1080/24725854.2023.2202226
    [25]

    J. Chen, X. Ye, W. Ma, D. Xu, Logic-Based Benders Decomposition for Order Acceptance and Scheduling on Heterogeneous Factories with Carbon Caps, Comput. Oper. Res., 168 (2024), 106706. https://doi.org/10.1016/j.cor.2024.106706

    doi: 10.1016/j.cor.2024.106706
    [26]

    J. Chen, X. Ye, N. Xie, Y. Sang, M. Sterna, Benders Decompositions for Order Acceptance and Scheduling in Additive Manufacturing, Eur. J. Oper. Res., 330 (2026), 745–759. https://doi.org/10.1016/j.ejor.2025.10.005

    doi: 10.1016/j.ejor.2025.10.005
    [27]

    C. Zheng, J. Yu, G. Wan, Online order acceptance and scheduling in a single machine environment, Comput. Oper. Res., 179 (2025), 107028. https://doi.org/10.1016/j.cor.2025.107028

    doi: 10.1016/j.cor.2025.107028
    [28]

    B. Ervural, A. Özaydın, Integrated order acceptance and inventory policy optimization in a multi-period, multi-product hybrid production system, Oper. Res. Perspect., 13 (2024), 100318. https://doi.org/10.1016/j.orp.2024.100318

    doi: 10.1016/j.orp.2024.100318
    [29]

    G. Xu, N. Wu, Y. Qiao, S. Zhang, Exact approach to joint order acceptance and non-permutation flow shop scheduling via logic-based Benders decomposition, Int. J. Prod. Res., (2026), 1–27. https://doi.org/10.1080/00207543.2026.2739603

    [30]

    T. Aouam, N. Brahimi, Integrated Production Planning and Order Acceptance under Uncertainty: A Robust Optimization Approach, Eur. J. Oper. Res., 228 (2013), 504–515. https://doi.org/10.1016/j.ejor.2013.02.010

    doi: 10.1016/j.ejor.2013.02.010
    [31]

    Y. Boulaksil, M. Grunow, J. C. Fransoo, Capacity Flexibility Allocation in an Outsourced Supply Chain with Reservation, Int. J. Prod. Econ., 129 (2011), 111–118. https://doi.org/10.1016/j.ijpe.2010.09.010

    doi: 10.1016/j.ijpe.2010.09.010
    [32]

    E. K. Bish, A. Muriel, S. Biller, Managing Flexible Capacity in a Make-to-Order Environment, Manag. Sci., 51 (2005), 167–180. https://doi.org/10.1287/mnsc.1040.0322

    doi: 10.1287/mnsc.1040.0322
    [33]

    A. A. Syntetos, M. Z. Babai, N. Altay, On the Demand Distributions of Spare Parts, Int. J. Prod. Res., 50 (2012), 2101–2117. https://doi.org/10.1080/00207543.2011.562561

    doi: 10.1080/00207543.2011.562561
    [34]

    S. Moon, C. Hicks, A. Simpson, The Development of a Hierarchical Forecasting Method for Predicting Spare Parts Demand in the South Korean Navy–-A Case Study, Int. J. Prod. Econ., 140 (2012), 794–802. https://doi.org/10.1016/j.ijpe.2012.02.012

    doi: 10.1016/j.ijpe.2012.02.012
    [35]

    S. Moon, A. Simpson, C. Hicks, The Development of a Classification Model for Predicting the Performance of Forecasting Methods for Naval Spare Parts Demand, Int. J. Prod. Econ., 143 (2013), 449–454. https://doi.org/10.1016/j.ijpe.2012.02.016

    doi: 10.1016/j.ijpe.2012.02.016
    [36]

    L. Berterottière, S. Dauzère-Pérès, C. Yugma, Flexible Job-Shop Scheduling with Transportation Resources, Eur. J. Oper. Res., 312 (2024), 890–909. https://doi.org/10.1016/j.ejor.2023.07.036

    doi: 10.1016/j.ejor.2023.07.036
    [37]

    Y. Dong, S. Jiang, L. Zhou, Z. Jiang, Y. Yu, A Joint Scheduling Approach for Production and Material Handling under Customized Manufacturing Paradigm, Eur. J. Oper. Res., 332 (2026), 730–747. https://doi.org/10.1016/j.ejor.2026.01.022

    doi: 10.1016/j.ejor.2026.01.022
    [38]

    J. N. Hooker, Planning and Scheduling by Logic-Based Benders Decomposition, Oper. Res., 55 (2007), 588–602. https://doi.org/10.1287/opre.1060.0371

    doi: 10.1287/opre.1060.0371
    [39]

    Özgün Elçi, J. N. Hooker, Stochastic Planning and Scheduling with Logic-Based Benders Decomposition, INFORMS J. Comput., 34 (2022), 2428–2442. https://doi.org/10.1287/ijoc.2022.1184

    doi: 10.1287/ijoc.2022.1184
    [40]

    G. Codato, M. Fischetti, Combinatorial Benders' Cuts for Mixed-Integer Linear Programming, Oper. Res., 54 (2006), 756–766. https://doi.org/10.1287/opre.1060.0286

    doi: 10.1287/opre.1060.0286
    [41]

    A. H. C. Eaves, B. G. Kingsman, Forecasting for the Ordering and Stock-Holding of Spare Parts, J. Oper. Res. Soc., 55 (2004), 431–437. https://doi.org/10.1057/palgrave.jors.2601697

    doi: 10.1057/palgrave.jors.2601697
    [42]

    Z. Gu, G. L. Nemhauser, M. W. P. Savelsbergh, Lifted Cover Inequalities for 0-1 Integer Programs: Computation, INFORMS J. Comput., 10 (1998), 427–437. https://doi.org/10.1287/ijoc.10.4.427

    doi: 10.1287/ijoc.10.4.427
    [43]

    Z. Gu, G. L. Nemhauser, M. W. P. Savelsbergh, Lifted Cover Inequalities for 0-1 Integer Programs: Complexity, INFORMS J. Comput., 11 (1999), 117–123. https://doi.org/10.1287/ijoc.11.1.117

    doi: 10.1287/ijoc.11.1.117
    [44]

    M. Queyranne, Structure of a Simple Scheduling Polyhedron, Math. Program., 58 (1993), 263–285. https://doi.org/10.1007/BF01581271

    doi: 10.1007/BF01581271
    [45]

    M. Queyranne, Y. Wang, Single-Machine Scheduling Polyhedra with Precedence Constraints, Math. Oper. Res., 16 (1991), 1–20. https://doi.org/10.1287/moor.16.1.1

    doi: 10.1287/moor.16.1.1
    [46]

    P. Baptiste, C. Le Pape, W. P. M. Nuijten, Satisfiability Tests and Time-Bound Adjustments for Cumulative Scheduling Problems, Ann. Oper. Res., 92 (1999), 305–333. https://doi.org/10.1023/A:1018995000688

    doi: 10.1023/A:1018995000688
    [47]

    J. N. Hooker, G. Ottosson, Logic-Based Benders Decomposition, Math. Program., 96 (2003), 33–60. https://doi.org/10.1007/s10107-003-0375-9

    doi: 10.1007/s10107-003-0375-9
    [48]

    V. Deshpande, A. V. Iyer, R. Cho, Efficient Supply Chain Management at the U.S. Coast Guard Using Part-Age Dependent Supply Replenishment Policies, Oper. Res., 54 (2006), 1028–1040. https://doi.org/10.1287/opre.1060.0327

    doi: 10.1287/opre.1060.0327
    [49]

    J. C. García-Benito, M. Martín-Peña, A Redistribution Model with Minimum Backorders of Spare Parts: A Proposal for the Defence Sector, Eur. J. Oper. Res., 291 (2021), 178–193. https://doi.org/10.1016/j.ejor.2020.09.014

    doi: 10.1016/j.ejor.2020.09.014
  • Reader Comments
  • © 2026 the Author(s), licensee AIMS Press. This is an open access article distributed under the terms of the Creative Commons Attribution License (http://creativecommons.org/licenses/by/4.0)

Metrics

Article views(41) PDF downloads(6) Cited by(0)

Article outline

Figures and Tables

Figures(5)  /  Tables(9)

/

DownLoad:  Full-Size Img  PowerPoint
Return
Return

Catalog